Turbo Sets - Process
Please let us know your requirement and we will find the best match for the vacant position of your project
Determination of job profile for the mechanical erection or commissioning, process engineer/ technician for turbines and related systems
Example Commissioning of a Steam Turbine
Preparation
- System check, walk down of system, comparison of PID (as built from erection) and field installations, check of cleanliness, accessibility and labeling
- Check and preparation of commissioning documentation
- Formal taking over from erection (transfer of liability) including the clear definition of boundaries, labeling of boundary limits and safe isolation, separation or closing of branches to connected systems that are not taken over yet
- Preparation for first filling and flushing
- Check installation and alignment of rotating machinery like pumps, fans,...
- Coordination with electrical and DCS teams and definition of priorities
- Ensure safe communication from field to switch gears and control room
- else
Commissioning of components
- First filling of vessels, pipes and equipment
- Check of supports and hangers
- Commissioning of systems like lube oil, control oil, jacking oil, hydraulic unit for steam reducing station, turning gear, evacuation system, sealing steam, etc.
- Signal check with switch gears (emergency stop) and control system/ control room indications
- else
System commissioning
- Filling of system and preparation for first start up.
- System start up and functional tests together with DCS
- Test of all protection features, automatic change over, alarm annunciation, "cold checks"
- Hot commissioning, i.e. first rolling, test of speed controller, over speed test, "hot" checks of further protection devices combined with the idle operation for excitation and synchronization checks
- System tuning and optimization for normal operation and in case of disturbances
- Documentation of results
- else